Inspection Status Information
Your search returned 52 result(s).
Project No.: SFR81398
Description: WB-Y/RES/SFR/2S/6BR/6.5BA LAL#1736/1691
Address: 17302 BALLMONT PARK DR
City: ODA 33556
Parcel: 001750.0606
Permit Issue Date: 4/6/2017
Permit Status: FINAL
Date | Inspection Item | Description | Inspector / Initial | Action | Notation |
---|---|---|---|---|---|
04/13/2017 | 102 | Footing Forms / Wall Footer | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | |
05/10/2017 | 105 | Slab | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | |
04/21/2017 | 107 | Stem Wall | Rod 18 / ASHWORTR | AP | |
05/19/2017 | 108 | Tie-in Survey | dtw / WATSOND | AP | Tie in survey approved with conditions. Request surveyor verify vertical datum reference and provide conversion for plan in NGVD. Structure lies in X. LGP FFE 44.6 NGVD29, survey lowest floor elevation 44.68 NAVD88. Setbacks meet AR zoning. Sealed survey is required. |
05/23/2017 | 108 | Tie-in Survey | dtw / WATSOND | AP | Approved signed and sealed |
05/31/2017 | 110 | Bond Beam or Lintel | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | |
06/22/2017 | 115 | Roof Sheathing | SZWEJKOWSKIJ / SZWEJKOWSKIJ | PA | West garage. |
06/27/2017 | 115 | Roof Sheathing | SZWEJKOWSKIJ / SZWEJKOWSKIJ | PA | All except East garage breezeway and 2nd story mid-section above the main entry. |
06/30/2017 | 115 | Roof Sheathing | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | ZIP system. |
06/30/2017 | 117 | Wall Sheathing | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | ZIP system. 2nd floor exterior wall strapping and 2nd floor back porch beams and columns connectors verified. |
02/08/2018 | 120 | Framing | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | |
09/07/2017 | 122 | Pre-Siding House Dry-In | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | Paper-back lath. |
08/30/2017 | 125 | Special Inspections | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | Framing inspection - all o.k. except MBa shower ceiling and plumbing wall (445 is PA due to parts being on back order). 120 approval needed after 445 is approved. |
09/01/2017 | 160 | Insulation | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | |
01/22/2018 | 198 | Roof Final | SZWEJKOWSKIJ / SZWEJKOWSKIJ | CO | HCC 12-5, (110.5) - Work not ready for inspection - 120 approval required (see 125 comments). |
02/08/2018 | 198 | Roof Final | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | |
04/30/2018 | 199 | Building Final | SZWEJKOWSKIJ / SZWEJKOWSKIJ | AP | |
05/08/2017 | 200 | Underground Electrical | TAPPJ / TAPPJ | AP | 4 Floor outlets - 2 Islands |
04/13/2017 | 205 | Ufer Ground | TAPPJ / TAPPJ | AP | |
02/26/2018 | 240 | Temp Power | TAPPJ / TAPPJ | AP | |
08/17/2017 | 250 | Electrical Rough-In | TAPPJ / TAPPJ | AP | |
08/24/2017 | 257 | Low Voltage Rough-in | TAPPJ / TAPPJ | AP | |
04/17/2018 | 297 | Low Voltage Final | RobertsLe / ROBERTSLE | CO | HCCC 8-8 (110.1) Locked out/ no access |
04/18/2018 | 297 | Low Voltage Final | TAPPJ / TAPPJ | AP | |
04/09/2018 | 299 | Electrical Final | TAPPJ / TAPPJ | AP | |
08/17/2017 | 350 | Mechanical Rough-In/HVAC | JONESML / JONESML | RT | ECC 403.2.2 SEALING-DUCTS/EQUIPMENT. SUPPLY AND RETURN BOXES NEED GASKET MATERIAL ON THEIR FACES WHERE THEY PENETRATE THE THERMAL ENVELOPE. HCC 8-1 PART A (107.3.1) -DOCUMENTS REQUIRED ON SITE. NO STAMPED ENERGY CALCS ONSITE. MIKE JONES 813-404-6802 |
08/18/2017 | 350 | Mechanical Rough-In/HVAC | EOW / WILLIAME | RTPD | |
08/22/2017 | 350 | Mechanical Rough-In/HVAC | JONESML / JONESML | AP | |
04/05/2018 | 399 | Mechanical Final/HVAC | ENGLISHJ / ENGLISHJA | AP | |
11/28/2017 | 400 | Sewer/Sewer Tie In | JIMENEZD / JIMENEZD | RT | FPC 312.2 - Drainage and vent piping test failed HCC 15-14 (110.5) - Work not ready for inspection. FORCE MAIN NEED LABLE.COLOR INDICATION SEWER |
04/09/2018 | 400 | Sewer/Sewer Tie In | GONZALEZP / GONZALEP | AP | |
04/12/2018 | 420 | Lawn Irrigation | GONZALEZP / GONZALEP | AP | |
11/28/2017 | 430 | Water Service | JIMENEZD / JIMENEZD | CO | FPC 312.5 - Water supply system test failed |
04/09/2018 | 430 | Water Service | GONZALEZP / GONZALEP | AP | |
08/28/2017 | 445 | Tubset/2nd Plumbing Rough In | JIMENEZD / JIMENEZD | RT | HCC 15-14 (110.5) - Work not ready for inspection.PLUMBERS STILL WORKING ON PROJECT. |
08/29/2017 | 445 | Tubset/2nd Plumbing Rough In | GONZALEZP#37 / GONZALEP | PA | MINUS, M.B. |
09/26/2017 | 445 | Tubset/2nd Plumbing Rough In | JIMENEZD / JIMENEZD | AP | |
05/05/2017 | 450 | Plumbing Rough-In / Main Drain | GONZALEZP / GONZALEP | RT | FPC 305 / P2603 - Pipe sleeves required and or not installed per code. |
05/08/2017 | 450 | Plumbing Rough-In / Main Drain | GONZALEZP / GONZALEP | AP | |
04/05/2018 | 499 | Plumbing Final | GONZALEZP#37 / GONZALEP | CO | SEE 430 AND 400 |
04/09/2018 | 499 | Plumbing Final | GONZALEZP / GONZALEP | AP | |
08/01/2017 | 550 | Gas Rough-In | JIMENEZD / JIMENEZD | AP | 7 DROPS: 1 DRYER,1 CT, FP. 4 OUTSIDE |
09/18/2017 | 555 | 2nd Gas Rough In | JIMENEZD / JIMENEZD | CO | HCC 15-14 (107.3.1) - Approved plans/documents required site. NEED GAS PERMIT |
09/19/2017 | 555 | 2nd Gas Rough In | JIMENEZD / JIMENEZD | AP | |
03/19/2018 | 560 | LP Tank Set | LITTLETOND / LITTLETOND | RO | computer issues |
03/19/2018 | 560 | LP Tank Set | LITTLETOND / LITTLETOND | CO | Computer issues |
03/20/2018 | 560 | LP Tank Set | GONZALEZP / GONZALEP | AP | |
04/17/2018 | 599 | Gas Final | GONZALEZP / GONZALEP | AP | |
04/24/2018 | 905 | Res LAL/Lot Grading/NPDES | RA / ALVAREZRE | AP | Final - Approved |
03/02/2018 | 21111 | FAX TECO (FOR OFFICE USE ONLY) | LD / DODSONL | TE | |
03/02/2018 | 21111 | FAX TECO (FOR OFFICE USE ONLY) | 9988 / 9988 | FAX | IVRS - Inspection :* |
04/30/2018 | 21115 | FAX CO (FOR OFFICE USE ONLY) | MAV / VAZQUEZM | AP |